Dear expert,
If a credit requires shipment of ‘100 tonnes of grade A quality steel scrap’ and states partial shipment is not applicable. A tolerance not to exceed 5% more or 5% less than the quantity of goods as per sub article 30(b) is applicable or not?
Regards
H jallouli
Does Sub Article 30(b), UCP600 Applies To 100 Ton Of Steel
-
- Posts: 113
- Joined: Tue May 14, 2013 7:53 pm
- First Name: Hachem
- Last Name: Jallouli
- Organization: BNA Bank
- Filter: Two Plus Two =: 4
- Location: Tunisia
- picant
- Posts: 2026
- Joined: Wed Aug 20, 2008 1:49 pm
applicable
Hi Pal,
Tonne is not a packing unit or individual item, isnt it?
Other comments appreciated
Ciao
Tonne is not a packing unit or individual item, isnt it?
Other comments appreciated
Ciao
-
- Posts: 40
- Joined: Sun Jul 07, 2013 6:42 pm
- First Name: thuy
- Last Name: van
- Organization: bank
- Filter: Two Plus Two =: 4
- Location: vietnam
UCP600 art 30 b
Tonne or MT would not be a type of packing unit or individual items. What you confuse here is that LC states partial shipment is not allowed, is that right? Art 30b does not mention partial shipment is allowed or not, so I think it is applicable whether partial shipment is allowed or not. That is to say, art 30b is applicable in this senario.
Regards
Regards
-
- Posts: 113
- Joined: Tue May 14, 2013 7:53 pm
- First Name: Hachem
- Last Name: Jallouli
- Organization: BNA Bank
- Filter: Two Plus Two =: 4
- Location: Tunisia
tolerance as per sub art 30(b)
If a credit stipulates
* quantity:100 tonnes of grade A quality steel scrap
* the unit price of one tonne of grade A quality steel scrap is for USD 100,
* and the credit amout is for USD 10 000,
A shipement of 95 tonnes will induce a drawing for USD 9500. In this case a document checker will pay, as per sub art 30(b), because the total amount of drawing does not exceed USD 10000.
But, a shipment of 105 tonnes will induce an invoice value for USD 10500. In this case a document checker will pay for only USD 10000 because a drawing in excess to the credit amount is not acceptable as per sub art 30(b).
Any comment would be highly appreciated
* quantity:100 tonnes of grade A quality steel scrap
* the unit price of one tonne of grade A quality steel scrap is for USD 100,
* and the credit amout is for USD 10 000,
A shipement of 95 tonnes will induce a drawing for USD 9500. In this case a document checker will pay, as per sub art 30(b), because the total amount of drawing does not exceed USD 10000.
But, a shipment of 105 tonnes will induce an invoice value for USD 10500. In this case a document checker will pay for only USD 10000 because a drawing in excess to the credit amount is not acceptable as per sub art 30(b).
Any comment would be highly appreciated