Dear Friend,
LC payment payment - 60 days from date of B/L - i.e. Maturity date for payment 15 March 2009.
But LC expired on 12 Feb 2008. How do we define LC still valid or what else.
Thanking you
Pradip Bhavsar
Validity of LC
-
- Posts: 4
- Joined: Tue Feb 17, 2009 9:15 pm
validity differ from payment
the issuing bank as well as the confirming bank have ultimate liability to effect payment at maturity date provided that the stipulated documents were presented within the credit validity and being found fully complied with lc terms and conditions
-
- Posts: 362
- Joined: Mon Jun 23, 2008 4:17 pm
- First Name: Olcay
- Last Name: Özcan
- Organization: Bank
- Filter: Two Plus Two =: 4
- Location: Turkey
Expiry for presentation not payment...
Hi friend,
Expiry date should be (in my opinion) defined as expiry date for presentation not for payment. .
Therefore, if presentation made before that date, payment may be later as per LC terms..
Refards
Expiry date should be (in my opinion) defined as expiry date for presentation not for payment. .
Therefore, if presentation made before that date, payment may be later as per LC terms..
Refards