CDCS Question On Article 32 of UCP600
Posted: Mon Aug 29, 2016 10:10 pm
Hi colleagues,
Need your opinion regarding below mentioned question:
A credit allowing partial shipments states following shipment schedule:
5000 units to be shipped between 01-15 January 2012
2000 units to be shipped between 16-31 January 2012
3000 units to be shipped between 01-15 February 2012
5000 units to be shipped between 16-29 February 2012
Which of the following shipment(s) under the credit is (are) complying?
I. 5000 units shipped on 13th January 2012
II. 1000 units shipped on 25th January 2012
III. 4000 units shipped on 15th February 2012
IV. 5000 units shipped on 19th February 2012
A. (I) only B. Both (I) and (II) C. (I), (II) and (III) D. All of the above
Thank u in advance
Gega
Need your opinion regarding below mentioned question:
A credit allowing partial shipments states following shipment schedule:
5000 units to be shipped between 01-15 January 2012
2000 units to be shipped between 16-31 January 2012
3000 units to be shipped between 01-15 February 2012
5000 units to be shipped between 16-29 February 2012
Which of the following shipment(s) under the credit is (are) complying?
I. 5000 units shipped on 13th January 2012
II. 1000 units shipped on 25th January 2012
III. 4000 units shipped on 15th February 2012
IV. 5000 units shipped on 19th February 2012
A. (I) only B. Both (I) and (II) C. (I), (II) and (III) D. All of the above
Thank u in advance
Gega