Page 1 of 1

2 AWBS WITH DIFFERENT DATE

Posted: Thu Mar 31, 2022 8:38 pm
by spx
Hi Friends ,
Need an understanding regarding below query
A presentation under the LC consisting of two AWBs under single presentation with different dates say AWB 1 is 15Mar2022 and AWB 2 is 17Mar2022, then what will be the maturity date if tenor is 30 days from AWB date.

Thanks

Re: 2 AWBS WITH DIFFERENT DATE

Posted: Fri Apr 08, 2022 6:35 pm
by picant
Hi Pal,

IMHO, it is applicable the ISBP 745 para B2 e iii, and the maturity is 30 days from 17mar2022.
Other comments appreciated
Ciao